Liberty Memorial Bridge
I-94 Business Loop Missouri River Highway Crossing
Bismarck, ND

Liberty Memorial Bridge

• Structure ID:
• Location: River Mile .
• River Elevation: 1,625 Feet
• Highway: I-94 Business Loop
• Daily Traffic Count:
• Bridge Type: Steel Box Girder With Concrete Deck
• Length: 2,369 Feet, 1,658 Foot Main Bridge, 285 Foot Longest Span
• Width: 84 Feet, 4 Lanes Plus 10-Foot Sidewalk
• Navigation Channel Width: Non-Navigable
• Height Above Water: 30 Feet
• Date Built: Started June 11, 2006, Projected Opening Summer 2008
The old Liberty Memorial Bridge is the large truss bridge shown in these photos. That bridge was completed in 1922. Designed for a 50 year life span, the bridge was 84 years old when construction on the new bridge began on June 11, 2006. The old bridge was very heavily traveled for a two lane bridge. In addition, the physical pounding from ever heavier trucks resulted in an old bridge that needed significant repair work. The state found that it was more economical to build a modern 4-lane bridge.

The new bridge is being built by Lunda Construction of Black River Falls, Wisconsin. These photos, from the fall of 2007, show the progress about one year into the project, and about 9 months from completion. The piers are built, the steel is installed on the approach spans, and the main spans are ready for steel. In this case, the main spans will be built from steel box girders. These are hallow steel boxes that are welded end to end. They have interal braces to keep them rectangular. There will be four main box beams in all, running the length of the bridge. The piers are made of concrete. They look like large capital lettter Y shapes, two side by side. The box girders will sit on the top of each point on each letter Y. From there, a rebar reinforced concrete deck will be installed.

The bridge will be 2,369 feet long overall. The main river bridge with the box girder configuration will be 1,658 feet long. A large concrete abutment will sit at each end of the main river bridge. The abutments will also have smaller approach spans to bring traffic up onto the main bridge section. These approach spans are important because there are road, park, marina, and housing traffic that needs to pass under these bridges. The brige is expected to be open for 4-lanes of traffic by late summer of 2008. The remaining construction and landscaping is planned to be finished by the end of fall 2008. The old bridge will be removed during the spring, summer, and early fall of 2009.


Liberty Memorial Bridge
Liberty Memorial Bridge
Liberty Memorial Bridge
Liberty Memorial Bridge
Liberty Memorial Bridge

Home  Return To Missouri River Structures Home Page
Photo and text by John A. Weeks III, Copyright © 2008, all rights reserved.
For further information, contact: john@johnweeks.com